• Installed at Methven on Ashburton Lyndhurst Irrigation Scheme
• Twin turbines supplying irrigation water to 5 adjacent farms. 235 L/sec low pressure for centre pivots and 110 L/sec at higher pressure for big guns
• Total turbine output 240 kW
• Installation replaced 4 diesel pumps and offset installation of a further 3 electric pumps
• Capital cost of approximately $600,000
• Annual electricity & diesel savings of approximately $150,000
• Crosstech Engineering was responsible for the design and supervision of total scheme and manufactured and installed the crossflow turbines and other associated mechanical components.